Fort Campbell Installation-Wide Outside and Inside Plant Build

Fort Campbell, KY/TN · Nov 2012 – Apr 2015

Scope

Survey and build of a new telecommunications backbone across Fort Campbell: duct bank, manholes and handholes, plowed and placed fiber, and inside plant work in 231 buildings.

Work performed

  • 233,000 ft of duct bank
  • 241 manholes and handholes
  • 8,000 ft of directional drilling and 1,090 ft of steel casing bore
  • 252,000 ft of direct-bury fiber plowed
  • 704,000 ft of cable placed
  • 10,000 fiber terminations and 18,000 fusion splices
  • Inside plant work in 231 buildings